Lach Huyen International Gateway Port, Japanese ODA Loans and a Public-Private Container Terminal
Lach Huyen is a deep-water port in Hai Phong on the northern coast of Viet Nam. It was built to meet growing container demand and the increase in the maximum size of container ships (JICA, 2016). JICA describes it as the first pilot public-private partnership (PPP) project between the Government of Viet Nam and the Government of Japan, in which the public portion was financed by Japanese ODA and the private portion was invested by a joint venture of Japanese and Vietnamese companies (JICA, 2020).
Approach
Public and private works were split. Japanese ODA loans funded the public infrastructure: soil improvement and reclamation for the terminal area, dredging, construction of revetments and a training dyke, and the Tan Vu-Lach Huyen Highway of about 15.63 km. A joint venture of Japanese companies and a Vietnamese company was to build the container yards, pier-type berths and cargo-handling equipment, and then operate and maintain the terminal (JICA, 2011; JICA, n.d.).
Loans were agreed in phases. JICA signed three phases of ODA loans for the port and the road and bridge components: JPY 20,995 million in November 2011, JPY 37,958 million in March 2014 and JPY 55,167 million in March 2016, a total of JPY 114,120 million (JICA, n.d.).
Long-term, low-interest terms. The 2014 and 2016 loans carry an interest rate of 0.1 percent a year, repayable over 40 years including a 10-year grace period (JICA, 2014; JICA, 2016).
Government agencies led delivery. The Ministry of Transport was the executing agency, with the Vietnam Maritime Administration responsible for the port and the Directorate for Roads of Viet Nam responsible for the road and bridge (JICA, 2011).
Results
The deep-sea port and related basic infrastructure opened in 2018. The public works included a 3,230 metre breakwater and a 7,600 metre sand protection dyke, and in 2020 the project received the Japan Society of Civil Engineers (JSCE) Innovative Technique Award, the first presented to a project in Viet Nam (JICA, 2020).
The private terminal, Haiphong International Container Terminal (HICT), opened on 13 May 2018. At opening, its shareholders were Saigon Newport Corporation (51 percent), Mitsui O.S.K. Lines (17.5 percent), Wan Hai Lines (16.5 percent) and the Itochu Group (15 percent). HICT had 750 metres of berth, 16 metres of water depth at berth and a capacity of 1.1 million TEU a year, and could receive container ships of up to 14,000 TEU (Saigon Newport Corporation, 2018).
Transferability
DMC governments can split a port project so that ODA or development bank loans fund the public works, such as breakwaters, dredging, reclamation and access roads, while a private operator funds the terminal equipment and runs the terminal.
Agreeing loans in phases lets finance follow the construction program. The lending terms and PPP structure at Lach Huyen came from a bilateral arrangement between the governments of Viet Nam and Japan, so they transfer only where a comparable lender and long-term government commitment are available.
Sources
All information used for this case study was based on publicly available resources.
- JICA. 2011. Ex-Ante Evaluation: Lach Huyen Port Infrastructure Construction Project (I). (opens in new tab)
- JICA. n.d. Ex-Ante Evaluation: Lach Huyen Port Infrastructure Construction Project (I) (II) (III). (opens in new tab)
- JICA. 2014. Signing of Japanese ODA Loan Agreement with the Socialist Republic of Viet Nam. Press release, 19 March 2014. (opens in new tab)
- JICA. 2016. Signing of Japanese ODA Loan Agreements with Viet Nam: Building infrastructure to strengthen international competitiveness and overcome vulnerabilities. Press release, 4 April 2016. (opens in new tab)
- JICA. 2020. Lach Huyen Port Infrastructure Construction Project Receives Innovative Technique Award. Press release, 30 October 2020. (opens in new tab)
- Saigon Newport Corporation. 2018. HICT: The First Deep-Water Terminal in the North of Viet Nam. 13 May 2018. (opens in new tab)